Renovation work

Dismantling, demolition and construction of the North Stand

The demolition of the North Stand will be carried out, whilst at the same time a separation will be introduced between the stands stretching along the touchlines and the stand behind the goal.

A security area will be installed around the separation points, with the construction site cut off by the security fencing in the North Stand.

The sections closest to spectators will be dismantled during the summer months or whenever there are no fixtures being staged at the stadium.

Once these steps have been completed, work will begin on building the new concrete structure and putting the prefabricated seating in place in the North Stand.