Remodeling of Anoeta

Stadium update

The txuri-urdin dream will become a reality soon. Anoeta’s remodeling continues advancing by leaps and bounds and  the new Anoeta will be set soon. Next, the current status of the renovation works will be explained in detail.

At present, the digging of the south stand is finished, the corner external pillars are being assembled and three cranes have been lifted in the south stand.

In the upcoming weeks, the following advances will take place:

-It is expected that by the end of January the foundations and the cement floor basement of the south stand will be executed. The perimeter walls of the south stand basement will also be completed.

-Digging of the tracks which are located in front of the east stand will be carried out by mid-February and mid-March. This will be made in order to continue building the pilings of the east stand.

-Digging of the tracks which are located in front of the west main stand will be carried out by mid-February and mid-March. This will be made in order to continue building the pilings of the west stand.